IGEM:VGEM/2008/Timeline

From OpenWetWare
Jump to navigationJump to search

Timeline

  • May
    • Get practice with the lab protocols we'll be using this summer and establish baselines for termination efficiency
    • Order the mutagenesis kit for genetic attenuators and the first gene for the bioplastic production
  • June
    • Transform and express the first bioplastic gene
    • Create and characterize the desired library of terminator mutants
  • July
    • Transform and express the second and third bioplastic genes
    • Synthesize the genetic attenuator project with the bioplastic production
  • August
    • Obtain all results by August 8
    • Finish presentation (and paper for publication?)
  • Fall
    • Project and part documentation, Biobrick DNA to IGEM by October 29
    • Jamboree on November 8-9!!