Week Starting 03/08: Aims

  • Lab induction & safety - Completed
  • Lab preparation - Completed
  • Design Primers - Completed: To be Checked
  • BioBrick Designs - Completed: To be Checked
  • Order (genes, clones, primers, assays) - Update needed
  • Timer Modelling - Completed
  • Assemble timer - Genetic timer no longer used
  • Dry lab tutorial - To be Completed
  • Choose Name for Project - Completed



Week Starting 27/07: Aims and Achievements

  • MIT Project Description - Completed
  • Assay Protocols - Completed
  • Cloning Strategies - Completed
  • Finish Genetic Circuit and BioBricks - Completed
  • Wet Lab Plan - Completed
  • Which genes will we PCR? - Completed
  • Gantt Chart - Completed