This page is for keeping track of what is going on with the design and construction of the new "Endolke / Smendy" labs at Stanford.
- Is all project funding in place? Yes (confirmed as of 4/23).
- Schedule 50% design review w/ Brian (confirmed for 9a June 2 at Stanford)
- First 2 hours are to go through shop drawings (DE and CDS should study existing plans before meeting)
- Equipment placement and so on, not cabinetry
- Second 1-2 hours is to work with Claire on lighting, color, and offices
- First 2 hours are to go through shop drawings (DE and CDS should study existing plans before meeting)
What are the next steps?
- Attend June 2 design meeting (All)
- Confirm location and funding of admin. office in Y2E2-254 (Raul)
- Inspect and select layout for CDS and DE offices (CDS, DE)