Royah Vaezi (talk | contribs) (New page: James Field: Aims: <b>Wet lab:</b> *Check plates from yesterday *Start cultures (5ml) for wednesday of all biobricks <b>Dry lab:</b> *Finish colanic acid assay and SLIC cloning strategy...) |
(No difference)
|
Latest revision as of 08:48, 15 August 2009
James Field:
Aims:
Wet lab:
- Check plates from yesterday
- Start cultures (5ml) for wednesday of all biobricks
Dry lab:
- Finish colanic acid assay and SLIC cloning strategy
Results:
Wet lab:
- Checked plates from Monday - pBAD failed to grow so re-plated. Others appeared fine.
- Completed miniprep prep for Wednesday.
Dry lab:
- Continued (but did not finish colanic acid assay protocol).
- Read up on but did not design primers for SLIC.
David Roche 04:39, 11 August 2009 (EDT)
Aims:
Dry Lab:
- Finish trehalose assay, and SLIC cloning strategy.
- Make sure M2 is completely finished.
- Nuri Purswani 04:40, 11 August 2009 (EDT):
Aims:
- Finish CRP-glucose promoter information: Cloning strategy
- Promoter assay
Dineka Khurmi 05:15, 11 August 2009 (EDT)
Aims:
- Finish promoter, Dam assays, and SLIC cloning strategy.
- Make sure M3 is complete.
Kun Xue 05:15, 11 August 2009 (EDT)
Aims:
- Finish restriction enzyme, Dam assays, and SLIC cloning strategy.
- Make sure M3 is complete.
Results:
- Did a RE and methylation assay, subject to approval
- Put up a cloning strategy to fit multiple cloning advantage of SLIC
- Looked through M1
Royah Vaezi
Dry Lab
- Helped Dineka and Kun with M3 assays.
Wet Lab
- Completed PCR of OtsB - failed to obtain bands on gel so this will be re-done.